Patch Set 5 for Oracle Primavera P6 EPPM R21.12

Patch Set 5 for Oracle Primavera P6 EPPM R21.12

| released in Support

Patch set 5 for Oracle Primavera P6 EPPM R21.12 is available for download from My Oracle Support. The patch set contains the patches from the previous service packs and patch sets. Prerequisite for the installation of the service packs is at least version P6 EPPM R21.12.0 or higher.

The patch set is certified for the JDK 1.8.0_311 Further supported JDK versions can be found in the Tested Configurations.

Version

Component

Bug ID

Title

21.12.5.0

WEB

34155470

GROUPING BY INTERVAL SHOWS NO DATA

34115700

INTERNAL-BP:REG 22.5: EPS VIEW- PROJECT BASELINE AND BASELINE DATA DATE COLUMNS NOT DISPLAYING CORRECT VALUES WHEN MORE THAN 500 PROJECTS

34100534

APPLY ACTUALS NOT WORKING IN P6 WEB

34098919

PRE : PSS - IMPORT PROJECT WITH HAVING SINGLEQUOTE IN THE IMPORTFILENAME , THROWS VALIDATION ERROR

34084195

FILTERS THAT CONTAIN DATES BRING BACK UNEXPECTED RESULTS

34036571

JAVASCRIPT CODE CAN EXECUTE THE /P6/REST/DICTIONARIES/LOAD/FINANCIALPERIODS REQUEST PASSING AN INVALID PARAMETER VALUE TEMPLATEID=UNDEFINED

34032030

21 FP - AFTER UPGRADE FROM VERSION 16.1 TO 20.12, CURRENT WEEK (CW) FILTERS ARE DEFECTIVE

34017083

PUBLISH JOB CRASH WHEN IT LOADS A HALF DELETED PROJECT WITH NULL PROJWBS DATA

33990010

CLICKING ACCEPT, REJECT, OVERRIDE, HOLD ON THE APPROVALS > STATUS UPDATES PAGE TRIGGERS A FULL DATA RELOAD WITH THE SAVE OPERATION POST REQUEST

33934925

PRE:OBS FOR WHICH USER DOESNT HAVE ACCESS CAN BE ASSIGNED AT WBS LEVEL WHILE IMPORTING A PROJECT

33810014

GLOBAL SEARCH AND REPLACE FAILS - THE CONVERSION OF THE DATA TYPE VARCHAR TO DATETIME PRODUCED AN OUT-OF-RANGE VALUE.

33784989

INEFFICIENT STATEMENT LOADING PROJECTS > EPS PAGE WHEN PROJECT BASELINE COLUMN ADDED TO GRID AND ENVIRONMENT HAS THOUSANDS OF PROJECTS WITH A DEFINED PROJECT BASELINE

TM

34015547

FP - BUG 33909508 - PERCENT COMPLETE VALUE IN TEAM MEMBER CHANGE WHEN SAVED INITIALLY

SRVS

34072158

WEB SERVICES READRESOURCEASSIGNMENTSPREAD NOT WORKING

P6PRO

34166600

XER IMPORT/EXPORT NOT IMPORTING OR EXPORTING CALENDAR EXCEPTIONS, NOTEBOOK DESCRIPTIONS WHEN DATA ELEMENT EXCEEDS 4096 CHARACTERS

34094396

FP - [ORACLE DB ONLY] UPGRADE SCRIPT LOGIC FROM 20.9 OR EARLIER RELEASES CAN CREATE FINANCIAL PERIOD WITH END_DATE THAT INCLUDES A TIMESTAMP OTHER THAN 00:00:00

34084187

BASELINE UPDATE PERFORMANCE ISSUE

34084170

WRONG ADDED BY USER APPEARING FOR MULTIPLE PROJECTS, CUSTOMER REQUESTING HOW/WHO MADE ADDED BY CHANGES

34076716

PPM JOB SERVICES FAILS XER EXPORT JOB - ERROR: ACCESS VIOLATION AT ADDRESS 0000000000F5657C IN MODULE ~PRMJOB.EXE~

34070223

P6 IS DISABLING THE MENU FOR NON-INTEGRATED PROJECTS AND NOT ENABLING IT AGAIN

34067946

IMPORT XML FAILS WITH ERROR ORA-00001: UNIQUE CONSTRAINT ADMUSER.PK_TASK VIOLATED

34056584

SQL SERVER DB UPGRADE FROM 20.12.2.0 TO 21.12.3.0 FAILS - ERROR IN RUN SQL SCRIPT SSPM_P201202.SQL

34049701

LONG START OF P6 PROFESSIONAL APPLICATION.

34032447

NON-ADMIN SUPERUSERS GETTING AN EXCEPTION ERROR WHEN ATTEMPTING TOOLS, SCHEDULE COMPARISON IN PVD

34006566

IMPORTING XER IS NOT DELETING ALL UNREFERENCED ACTIVITY RELATIONSHIPS

proadvise GmbH l Brühlweg 4 l 73663 Berglen

Newsletter

Register here for our newsletter and secure your knowledge advantage!

Register now

Copyright © 2020 proadvise.com - All rights reserved.
Design and programming webart-IT UG (haftungsbeschränkt)