Patch set 9 for Oracle Primavera P6 EPPM R20.12 is available for download from My Oracle Support. The patch set contains the patches from the previous service packs and patch sets. Prerequisite for the installation of the service packs is at least version P6 EPPM R20.12.0 or higher.

The patch set is certified for the JDK 1.8.0_271 Further supported JDK versions can be found in the Tested Configurations.

Version

Component

Bug ID

Title

20.12.9.0

WEB

33330802

SCORECARD PORTFOLIO VIEW PROJECT NAME HYPERLINKS DO NOT OPEN THE PROJECT BEFORE REDIRECTING TO THE ACTIVITIES PAGE

33319506

FP UPDATE USERS FROM LDAP WITH SELECT ALL USERS - RETURNS NO RESULT

33290833

FP - ERROR: ORA-01795: MAXIMUM NUMBER OF EXPRESSIONS IN A LIST IS 1000 WHEN COPY/PASTE PROJECTS

33277306

P6 WEB APPROVALS TAB TAKES MINUTES TO LOAD

33251166

SORT BY ACTIVITY CODE COLUMN NOT WORKING

33251021

SEARCH FOR ACTIVITY CODE VALUES NOT WORKING IN ACTIVITIES VIEW

33225658

STACKED HISTOGRAM IN RESOURCE ANALYSIS IS NOT SORTING ALPHABETICALLY

33210278

TYPE AHEAD SEARCH IN PROJECT CODE FIELD IN GRID VIEW OF EPS DOES NOT RECOGNIZE CHILD PROJECT CODE VALUES

33197195

FP DURATION DOES NOT CHANGE WHEN DRAGGING ACTIVITY START ON GANTT CHART

33180166

HIERARCHICAL QUERIES CAUSE PERFORMANCE ISSUE WHILE LOADING EPS PAGE WHEN GROUPING INTERVAL IS ONE

33270003

FP - WHEN LOADING ACTIVITES USING P6 API ALL TASKRSRC FOR THE PROJECTS ARE LOADED DURING EACH BATCH

33273500

FP PRIMAVERA WEB SERVICES SYNCHRONIZATION ERROR

33294152

BP- INVALID OBJECT LISTED FOR 20.12.5 NEW INSTALL OR UPGRADE IN 12.1.0.2 ORACLE DB

33173548

20 BP - P6 (WEB) AND P6 PROFESSIONAL USE DIFFERENT RESOURCE CALENDAR WORKTIME WHEN CALENDAR HAS NULL CALENDAR.CLNDR_DATA BLOB FIELD

33279324

BP-CANNOT DOWNLOAD EXCEL XLSX FROM GLOBAL AND PROJECT SECURITY PROFILE PAGES

TM

33279132

[OCI MIGRATION ISSUE] ERRONEOUS EMAIL DETAILS FROM TEAM MEMBER VIEWER EMAIL SENDING FUNCTIONALITY

SRVS

33246025

JAVA.LANG.ARRAYINDEXOUTOFBOUNDSEXCEPTION OR JAVA.LANG.NULLPOINTEREXCEPTION SUMMARIZING PROJECT WHICH USES DIFFERENT FINANCIAL PERIOD CALENDAR THAN PROJECT BASELINE

33214484

ERROR IN PARSING THE DATE SELECTING UPDATE HISTORY ON ACTIVITIES VIEW FOR MULTIPLE USERS AND PROJECTS

32883218

SOME P6 PROJECT NOTEBOOK TOPICS PUBLISHING AS 'SPAN>'

P6PRO

33219586

IMPORT XLSX FAILS FOR SPECIFIC PROJECT

33159081

TIME DEFAULTS TO 00:00 WHEN DISABLING DISPLAY TIME IN USER PREFERENCES

33155553

SCHEDULE LOG LOCATION POINTING TO NETWORK DRIVE CAN DEGRADE OVERALL PERFORMANCE WITH SCHEDULING OPERATION

33067059

FS RELATIONSHIPS ARE CREATED WHEN ATTEMPTING TO CREATE SS, SF OR FF RELATIONSHIPS IN THE GANTT CHART

33244525

XML IMPORT – ADVANCED OPTIONS - MISSING OPTION TO “MOVE TO PROJECT” CALENDARS/CODES UNDER ACTION.

33231679

FP - SUMMARIZE PROJECT FAILED

33220683

IN P6 PROFESSIONAL PAGE SETUP > OPTION TAB WHEN BREAK PAGE EVERY GROUP IS SELECTED BUT DISABLED RESULTS IN PAGE BREAKS AFTER EACH ACTIVITY ROW

33219973

ACTIVITIES ARE NOT IMPORTED WHEN IMPORTING PRIMAVERA XML FILE

33210351

LAYOUT REORGANIZES EVEN WITH DISABLE AUTO-REORGANIZATION ENABLED

33173377

SHOW GRAND TOTALS PREVENTS EMPTY EPS NODES FROM BEING DISPLAYED

33121448

EVENT CODE: AVAA0-0396-F CHANGING THE FILTER ON THE PROJECT VIEW FROM CURRENTLY OPEN TO ALL

33037753

WBS ELEMENTS ARE NOT COPYING WPS & DOCS WITH ACTIVITES BETWEEN PROJECTS WHEN THAT OPTION IS SELECTED

proadvise GmbH l Brühlweg 4 l 73663 Berglen

Newsletter

Register here for our newsletter and secure your knowledge advantage!

Register now

Copyright © 2020 proadvise.com - All rights reserved.
Design and programming webart-IT UG (haftungsbeschränkt)