Patch Set 23 for Oracle Primavera P6 EPPM R18.8

Patch Set 23 for Oracle Primavera P6 EPPM R18.8

| released in Support

Patch Set 23 for Oracle® Primavera P6 EPPM is available for download at My Oracle® Support. The patchset contains all patches from previous service packs and patchsets. Requirement for installing this patchset is an existing version of P6 EPPM 18.8.0 or higher.

The patchset is certified for JDK 1.8.0_181. Other supported JDK-versions are listed within the Tested Configurations.

 

Version

Component

Bug ID

Title

18.8.23.0

WEB

32526079

PROMPTED TO SAVE VIEW WHEN NO CHANGES HAVE BEEN MADE

32467031

COLUMN ORDER WHEN EDITING SCORECARD IS NOTE SAVED

32484407

PRIMAVERA GATEWAY RESOURCE ASSIGNMENT UPDATE ISSUE

32465428

ADD/EDIT/DELETE RESOURCE ASSIGNMENTS FOR RESOURCE PLANNING STILL DISPLAYS IN ASSIGNED PRIVILEGES COLUMN AFTER UPGRADE FROM 8.3.5 TO 18.8.19

32301439

DASHBOARD PORTFOLIO VIEW SCORECARD PORTLET PERFORMANCE PERCENT COMPLETE NOT SUMMARIZING AS EXPECTED

32252243

JAVA.LANG.INDEXOUTOFBOUNDSEXCEPTION LOADING EPS VIEW THAT CONTAINS HIERARCHICAL GROUPING AT SPECIFIC GROUPING LEVEL WHEN UDF ADDED AS COLUMN AND THE GROUPING LEVEL IS STORED AS STRING

32244406

BP - ON P6 WEB RISKS COST COLUMN SHOWS INCORRECT DECIMAL AND DIGIT GROUPING SYMBOL

31891886

REPETITIVE SQL EXECUTED ONE TIME PER PORTFOLIO DEGRADING OVERALL PERFORMANCE LOADING 'MANAGE PORTFOLIO' WINDOW

31647055

TIMESHEET APPROVAL TAKES TOO LONG TO LOAD AND BECOME UNRESPONSIVE

31391670

HARD CODE FIRST_ROWS HINT FOR TWO DYNAMIC SQL STATEMENTS WHICH LOAD PROJECT AND EPS DATA THROUGH /P6/REST/PROJECTS/GRIDDATA/LOAD

32605577

FP FOR BUG 32469119 - ERROR ILLEGAL CHARACTER ((CTRL-CHAR, CODE 19)) INVOKING THE IMPORTSERVICE USING ZIP FORMAT WHEN PROJECT DATA INCLUDES A DASH CHARACTER

TM

32409352

IN V18.8.X TEAM MEMBER TIMESHEETS WHEN SELECTING A NEW TIMESHEET PERIOD THE DEFAULT PERIODS LISTED ARE IN YEAR 2018, UP TO 2 YEARS BACK

SRVS

32147412

TASK_COPY_PKG.TASKPRED_COPY PACKAGE PROCEDURE CAN RUN SLOWLY WHEN OPTIMIZER USES HASH JOIN

32073001

DELETE PUBLISHED DATA JOB NOT REMOVING DATA FROM ALL PROJECT SPECIFIC EXTENDED SCHEMA TABLES

32152346

OPTIMIZATION FOR A STATEMENT RUN DURING COPY/PASTE OR BASELINE CREATION SERVICE

P6PRO

32378570

NOTEBOOK TOPIC DISPLAYS TEXT AFTER APPLYING FILTER, THEN OPENING UP A DIFFERENT PROJECT

32110091

WHEN ASSIGNING RELATIONSHIPS, FOCUS MOVES TO ASSIGNED ACTIVITY

31523976

SIGNIFICANT ROW CONTENTION WHEN SCHEDULING

31186436

THE CONVERSION OF A VARCHAR DATA TYPE TO A DATETIME DATA TYPE RESULTED IN AN OUT-OF-RANGE VALUE.

31074956

CHANGING ACTIVITY CALENDAR TO A CALENDAR WITH NON-WORK TIME CAUSES RESOURCE ASSIGNMENT DURATION TO SET TO 0

32536084

MISSING DATA IN RISKS

32528420

FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

32503840

RESOURCE ASSIGNMENT LAYOUT SHOWS DASHES INSTEAD OF NUMBERS AT SUMMARY LEVEL WHEN PRINTING

32321472

ERROR SAVING MODIFIED UN/CEFACT XML TEMPLATE <DATE>T<TIME> IS NOT A VALID DATE/TIME VALUE

32244361

P6 PROFESSIONAL HANGS WHEN SELECTING MODIFY BUTTON IN HEADERS FOOTERS AND NOTEBOOK TOPICS

32241070

MSP XML IMPORT ERROR - VALUE FOR FIELD HOURSPERYEAR IN CALENDAR MAY NOT BE SET TO GREATER THAN 8784.

32239088

RESOURCEOBJECTID OR ROLEOBJECTID MUST BE SET WHEN CREATING RESOURCEASSIGNMENT OBJECTS

32213713

FROM P6 UN/CEFACT XML EXPORTS BLANK EARLY START, EARLY FINISH, LATE START, AND LATE FINISH DATES WHEN ACTUAL DATES EXIST FOR LOE & WBS SUMMARY TYPES

31664210

SELECTING FINISH ON A STARTED ACTIVITY THEN MOVING THE FINISH DATE AHEAD CAUSES THE HH:MM TIME VALUE (16:00) TO REVERT TO MIDNIGHT (00:00)

32556703

EXPORT LAYOUT FROM VISUAIZER FAILS WHEN THE LAYOUT NAME CONTAINS A FORWARD OR BACKWARD SLASH

32103796

IMPORTING XER FILE TRUNCATES FRONT OF NAME

32352701

SCROLLING IS SLOW ON PROJECT PAGE (IN ADDITION TO LOADING OF PROJECT PAGE FROM ANOTHER PAGE, SUCH AS ACTIVITIES) WHEN PROJECT OPENED AND GANTT CHART IS DISPLAYED OR TABLE CONTAINS DYNAMIC COLUMN

32202629

P6PRO TAKING 10 SECONDS TO SELECT EPS NODES THAT HAVE LARGE NUMBER OF CHILDREN

proadvise GmbH l Brühlweg 4 l 73663 Berglen

Newsletter

Register here for our newsletter and secure your knowledge advantage!

Register now

Copyright © 2020 proadvise.com - All rights reserved.
Design and programming webart-IT UG (haftungsbeschränkt)