Patch Set 20 for Oracle Primavera P6 EPPM R21.12

Patch Set 20 for Oracle Primavera P6 EPPM R21.12

| released in Support

Patch Set 20 for Oracle Primavera P6 EPPM R21.12 is available for download from My Oracle Support. The patch set contains the patches from the previous service packs and patch sets. Prerequisite for the installation of the service packs is at least version P6 EPPM R21.12.0 or higher.

The patch set is certified for the JDK 1.8.0_311 Further supported JDK versions can be found in the Tested Configurations.

Version

Component

Bug ID

Title

21.12.20.0

WEB

36735447

[BACKPORT] ERROR 'TOTAL FLOAT MUST BE BETWEEN 0D AND 12,500,000,000D' WHEN CHANGING ACTIVITY WITH NEGATIVE TOTAL FLOAT WHEN 10+ PROJECTS OPEN AND RELATIONSHIP TAB LOADED ON BOTTOM GRID

36650895

P6 EPPM CAPACITY PLANNING CHART DISPLAYING WITH TOO MANY DECIMALS PLACES WHEN SET TO SPREADSHEET (COSTS & UNITS) OR STACKED HISTOGRAM (COSTS)

36606940

EPS PAGE > CODES TAB > ASSIGN PROJECT CODE WINDOW INCORRECTLY MOVES CODE TYPE AS CHILD OF ANOTHER CODE TYPE WHEN CLICKING EXPAND

36523511

[BACKPORT] MULTIPLE ISSUES DISPLAYING EPS DATA ON PROJECT PAGE WHEN CUSTOM FILTERS ARE APPLIED

36429140

UNABLE TO USE THE FILL DOWN FUNCTION IN THE RESOURCE TAB

TM

36625776

BP-TEAM MEMBER FAILED TO LOAD

36620928

ENHANCE P6 MOBILE TO READ/WRITE CERTAIN USER PREFERENCES FROM USERSET TABLE

36563242

TM_LOAD_NONMILESTONEACTIVITIES_ERROR OCCURS WHEN LOADING ACTIVITES IN TEAM MEMEBER

SRVS

36557707

[BACKPORT] PERFORMANCE ISSUE WITH PUBLISH SECURITY GLOBAL SCHEDULED SERVICE (STEP 3)

36515211

PRIMAVERA JOB SERVICES PUBLICATION ARBITER JOB STOPS RUNNING WHEN CLOCKS GO FORWARD 1HR IN SPRING FROM GMT TO BST

36410036

[BACKPORT] PUBLISH SECURITY GLOBAL SCHEDULED SERVICE NOT UPDATING COST FLAG FOR NON-GLOBAL SUPERUSERS WHEN SECURITY PROFILE CHANGES ALLOW OR DISALLOW ABILITY TO VIEW COST

P6PRO

36671707

XML IMPORT OPTION TO FILL DOWN NOT WORKING

36400194

COMMIT CHANGES ENABLE AFTER COPY PASTE ACTIVITIES AND ITS CAUSING CREATING OF DUPLICATE ACTIVITIES IN MULTI USER SCENARIO.

36683847

GANTT CHART AND ACTIVITY TABLE ARE MISALIGNED AFTER ADDING NEW ACTIVITY

36671902

BP MICROSOFT PROJECT XML EXPORT DATA IS INVALID FOR MICROSOFT PROJECT WHEN USING SPECIAL CHARACTERS

36671700

TIMESCALED LOGIC DIAGRAM TAKES A LONG TIME TO LOAD IN VISUALIZER

36325501

ERROR RECEIVED VTDCF-1987-A WHEN SCHEDULING PROJECTS

35177052

LARGE XML FILE IMPORT PERFORMANCE

proadvise GmbH l Brühlweg 4 l 73663 Berglen

Newsletter

Register here for our newsletter and secure your knowledge advantage!

Register now

Copyright © 2025 proadvise.com - All rights reserved.
Design and programming webart-IT UG (haftungsbeschränkt)