Patch Set 10 for Oracle Primavera P6 EPPM R19.12

Patch Set 10 for Oracle Primavera P6 EPPM R19.12

| released in Support

Patch set 10 for Oracle Primavera P6 EPPM R19.12 is available for download from My Oracle Support. The patch set contains the patches from the previous service packs and patch sets. Prerequisite for the installation of the service packs is at least version P6 EPPM R19.12.0 or higher.

The patch set is certified for the JDK 1.8.0_231 Further supported JDK versions can be found in the Tested Configurations.

Version

Component

Bug ID

Title

19.12.10.0

WEB

31948329

FP - ERROR FAILED SAVING USERS DATA WHEN TRYING TO SAVE A NEW USER WITH OBS ASSIGNMENTS

31931920

CODE REFACTORING FOR BUG 31373776 - PUBLISH CHECK BOX IS NOT ENABLED AUTOMATICALLY IN DEFINE BASELINES FOR NEW BASELINES

31924482

19FP - NULL FOR FINISHDATE IN P6BLPROJECT, NULL FOR STARTDATE AND FINISHDATE IN P6BLWBS

31921200

PERFORMANCE ISSUE WITH EPS PAGE ISUNDER FILTER

31887310

DRAGGING GANTT BAR START EARLIER DOES NOT CHANGE DURATION AS SHOWN

31887070

RESOURCES DO NOT APPEAR IN ASSIGN RESOURCE DIALOG WHEN ACTIVE RESOURCES FILTER USED

31869943

BP: PRE209 : FILTERING WITH LARGE NUMBER OF PROJECTS GETS UNRESPONSIVE ON RISK PAGE

31867958

PRE:DB CHANGE -EXPORTING LARGE VOLUME OF DATA TO EXCEL FROM RESOURCE ASSIGNMENTS IS TAKING LONG TIME

31865677

IN P6 WEB F9 SCHEDULING DIALOG UNCHECKING CHECKBOX DISPLAY SCHEDULING LOG UPON COMPLETION DOES NOT STAY UNCHECKED

31796160

ASSIGN ROLE/RESOURCE DISABLED IN ACTIVITY DETAILS BUT NOT DISABLED IN CONTEXT MENU

31777030

GROUPING THEME GOES BACK TO DEFAULT OPTION

31708267

ACTIVITIES PAGE - VIEWS WITH PROJECT UDF AND PROJECT CODES ARE GETTING CORRUPTED UPON SUMMARIZATION

31142643

CHILD JOB FAILING DUE TO SUMMARIZATION BEING DISABLED SHOULD HAVE A STATUS OF JS_COMPERROR NOT JS_FAILED

31858888

SR 3-23971336871: NOT ABLE TO GET ANY SPREAD VALUES ( CUM REMAINING LATE TOTAL COST) - P6 WEBSERVICES

31612831

BUG 31558730 - SOME FIELDS ARE NOT CORRECTLY REFRESHED IN THE ACTIVITY SHEETS

31907949

PPM TO EPPM MIGRATION DISABLING ADMINISTRATION TIME PERIODS FLAG AND RESETTING ALL CALENDAR TIME PERIODS TO ADMINISTRATIVE TIME PERIODS

TM

31925944

19FP - TIMESHEET REJECTED IN P6 WEB SHOWS INCONSISTENT BEHAVIOR IN TEAM MEMBER

SRVS

31928287

ADDITIONAL IMPROVEMENT (PERFORMANCE) TO 'PUBLISH SECURITY' STEP 3 DELETE SQL

31802334

INTERNAL-FP:RESOURCE PUBLICATION SERVICES ARE VERY SLOW AND SOMETIMES DEADLOCK ERROR OCCURS

31578683

SQLSERVER IMPLEMENTION -ERROR UNIQUE CONSTRAINT ADMUSER.PK_SETTINGS VIOLATED IN CONCURRENT INSERT

31377855

PX RESOURCE ROLE ASSIGNMENT SPREAD JOBS FAILING

P6PRO

31935547

ERROR WHILE USING REDEFINE_TABLES.BAT FOR P6 PPM DATABASE

31918210

PERFORMANCE DEGRADATION EMULATING FOCUS OF SELECTED BAR ON ACTIVITIES GANTT CHART BARS WINDOW THROUGH SECURE GLOBAL DESKTOP

31898696

BAR OPTION SHOW BAR FOR GROUPING BAND OF SUMMARY BAR GETS UNTICKED AUTOMATICALLY

31879857

IMPORTING LARGE XML TO PROFESSIONAL FAILS WITH INCORRECT ERROR SEC2T-3983-1 THE FILENAME OR EXTENSION IS TOO LONG.

31876915

ACTIVITIES ARE MOVED TO AN EPS FROM ITS ORIGINAL WBS NODE AFTER MODIFYING THE ACTIVITY RELATIONSHIP

31917975

ENTRIES DO NOT ALLOW INPUT IN RESOURCE ASSIGNMENTS VIEW

31892979

ACTIVITY ADDED BY COLUMN DISPLAYS DIFFERENT USER

31870585

THE TEXT SCHEDULE IS NOT VISIBLE ON THE BUTTON WHEN WE USE THE RUSSIAN LANGUAGE

proadvise GmbH l Brühlweg 4 l 73663 Berglen

Newsletter

Register here for our newsletter and secure your knowledge advantage!

Register now

Copyright © 2020 proadvise.com - All rights reserved.
Design and programming webart-IT UG (haftungsbeschränkt)